Data Center
Growth fueled by experienced team and proven process. Global companies who trust us.
Data Center Build-out Checklist
Data centers must deliver high availability of all their systems to be successful. This checklist outlines the process to setup and install cabling for a data center correctly.
Scope of Work (SOW):
- General Scope of Work and overview of the entire project
- Include a description of the services required to complete the build
- Details included for each piece of equipment
- Staging requirements
- Labeling requirements
- Power up and burn-in requirements
- Module installation requirements
- Cabling requirements for each port
- Cable labeling requirements
- Logical requirements
- Packing requirements
- Shipping requirements
- Additional instructions for the various build and engineering teams.
Level Of Effort (LOE):
- Determine the Level of Effort required to complete the build
- Determine the window of time you have to build on-site
- Determine how many technicians and engineers you will need for the duration of the project
- Each task will need an estimated time associated
- PMs and Project Engineers will include the time required to design and manage the project
- Receiving, Inventory and asset management
- Pre-installation activities such as smoke test or
- Staging, Rack, and stack
- Cabling and Labeling
- Logical configuration
- A total estimate will be calculated for sales
Bill Of Materials (BOM):
Have a detailed Bill of Materials and identify lead times so orders are placed in time to minimize any risk of missing or late equipment.
- Racks and Cabinets and associated hardware
- Network, Systems and Storage Equipment
- Power and Network Cables
- Other non-serialized hardware
Data Center Location:
Select a Data Center location based upon:
- Location in relation to users, service providers, historic record of natural disasters and risks of other human events
- Power reliability, availability, and redundancy
- Security, both physical and logical
- Space for current build and future growth
Rack Elevations:
Determine elevation early so the cable BOM will be accurate and the installation team will know how the equipment will be mounted.
- Excel front and rear
- Visio front and rear
Cable Matrix:
- Excel format is recommended for ease of use and making changes
- Cable labeling requirements
- Wiring diagrams
Logical Configuration:
- OS or Firmware upgrade/downgrade
- Configurations and Logs
- BIOS Settings
- RAID Configuration
- Management IP
- Automation QA output
Product Information:
- Product specifications
- Product or materials special handling instructions
- Submittals used to sell products to customer
Proof Of Concept/First Article Build (POC/FAB):
- New rack builds will require a POC/FAB for the best design
- This may take several extra days to determine the final design
- For custom length cabled racks a fully built rack can help determine cable lengths without
unneeded extra slack - This is also essential for testing network architecture, configurations or compatibility prior to deployment
- POC is not required for rack builds that have a proven design
Project Plan:
- The on-site date required by the customer will dictate the shipping and deployment dates
- The LOE will determine the project plan working backward from the completion date with extra time to
mitigate the risk of missing deadlines. - The BOM and equipment will need to be ready and in the loading dock, storage area or pre-stage area
prior to the first day of the build. - Any delays in equipment or information may delay the project plan milestones or completion date.
Work Book:
- Work books are developed as a comprehensive as-built document fore very rack build
- These tabs/sheets are standard for rack build project workbooks
- Project Title and Project Team
- Revision Control
- Task Checklist
- Customer Data (provided by customer)
- Rack Design
- Rack Elevation
- Cable Matrix
- QA/QC Checks
- BOM/Ship Sheet